Client: Plocher Construction/ Metropolitan Sewer District
Location: St. Louis, MO
Project: Coldwater Creek Final Clarifier Replacement

Scope of Work: Provide clean saw cut lines along edges of clarifier channels that were being demolished.

Challenge: Cutting 30” thick trough flush with wall that was to remain and cutting through an 8’ wide x 12’ tall effluent chamber with steel piping running through it.